新問題 14
The amount of an advance payment guarantee provided for pursuant to FIDIC Red and Yellow Books (both editions) may be reduced as of:

 
 
 
 

新問題 15
Is the Employer obliged under FIDIC Silver Book (edition 1999) to describe which Documents are to be submitted to the Employer? (1 correct response applies)

 
 
 
 

新問題 16
If defects are identified during the Tests on Completion, which one of the following options is not available to the Parties under the Contract?

 
 
 
 

新問題 17
Under the FIDIC Red, Yellow, and Silver Books (both editions), the Contractor has a contractual obligation to submit a Value Engineering Proposal. Such proposal shall be prepared at the cost of the Employer. Are both these statements true or false?

 
 

新問題 18
You are the Contract Manager in a highway project using FIDIC Red Book (edition 1999). You work for the Employer- a highway management agency. During the tender period, you are informed of a specific Commencement Date required by the directors of the agency. Which two of the following approaches to inform the tenderers of this date are clearly and unambiguously drafted?
Choose all of the correct answers (multiple possibilities).

 
 
 
 

新問題 19
You are the Contract Manager for the Engineer in a hospital project using FIDIC Yellow Book (edition 2017).
The Employer demands perfection in the project’s design and construction quality. There are many Variations initiated by the Employer during design and construction. Which one of the following is considered to be a valid Variation?

 
 
 
 

新問題 20
The Contractor is entitled to an advance payment, it has obtained such payment and it has not yet been entirely paid back. Under FIDIC Red Book (edition 1999), in which two situations will the outstanding balance of the advance payment become immediately due?
Choose all of the correct answers (multiple possibilities).

 
 
 
 

新問題 21
Under the FIDIC Construction Contract, which one of the following statements is correct?

 
 
 
 
 

新問題 22
The Contractor is entitled to an advance payment. Applying FIDIC Red Book (edition 1999), which two of the following statements are correct?
Choose all of the correct answers (multiple possibilities):

 
 
 
 

新問題 23
FIDIC Red, Yellow, and Silver Books (both editions) contain a provision for the Engineer or Employer to instruct the Contractor to employ a subcontractor, thereby also permitting the Contractor to refuse to employ such proposed subcontractor on the basis of a reasonable objection by a notice. Is this statement true or false?

 
 

新問題 24
Which of the following form a Contractor’s entitlement, in case the Contractor does not receive an interim payment within the allocated contractual deadline for payment? (2 correct answers apply) Choose all of the correct answers (multiple possibilities).

 
 
 
 
 

新問題 25
Which one of the following is not a required document to be submitted by the Contractor if the Employer requests a proposal, prior to instructing a Variation, for FIDIC 2017 Yellow Book?

 
 
 
 

新問題 26
Regarding the FIDIC Red Book (edition 1999), which two statements are true?

 
 
 
 

新問題 27
Under both FIDIC Yellow Book (YB) and Silver Book (SB) (edition 1999), if the Engineer (YB) / Employer (SB) instructs the Contractor based on Sub-Clause 8.6 to provide a revised programme, the acceptance by the Engineer (YB) / Employer (SB) of a revised programme with a completion within Time of Completion entitles the Contractor to a payment of the needed extra costs. Is this statement true or false?

 
 

新問題 28
Applying FIDIC Silver Book (edition 1999), which one of the following elements shallnotform part of the time Programme/revised programme?

 
 
 
 

新問題 29
Which one of the following claim events does NOT allow profit?

 
 
 
 
 

新問題 30
Which two of the following statements are correct, regarding the Programme under FIDIC Red, Yellow and Silver Books (edition 2017)?
Choose all of the correct answers (multiple possibilities).

 
 
 
 

新問題 31
You are the Contract Manager of the Employer’s Representative in a Thermal Power Plant Project. The Contract for this project is EPC Turnkey Contract using the FIDIC Silver Book (edition 2017) with a Contract Price of 28 million USD. The Employer’s Requirements require that: “the Contractor design in accordance with international and national technical regulations, and standards, [etc.]”.
For piling works, the Employer’s Requirements state that the Contractor will design according to a specific national standard for piling works NTS-PW-01. After all piles for the jetty have been installed, a pile load test on lateral bearing capacity shows that actual lateral bearing capacity is much lower than the calculated lateral bearing capacity. It was later revealed by the Technical Standard Committee that there was a typo mistake during preparation of the NTS-PW-01 (translated from a foreign standard). The lateral bearing capacity of installed piles had been substantially overestimated as a result of this typo. Contractor submits a claim for
200,000 USD regarding extra costs for installing additional piles as a result of errors in the Employer’s Requirements.
In the hydrological information of Site Data provided by the Employer, the annual high water level is 4.0m.
However, during the design stage, with updated data from local stations along the rivers, the Contractor found out there was a mistake in the calculation. The annual high water level should be 4.5m. As a result, the Contractor has to design and build additional flood walls along the river to protect the Plant from flooding.
The Contractor claims an amount of 300,000 USD to construct the flood wall, based on Unforeseeable difficulties.
As the Employer’s Representative, after you have consulted with both Parties but failed to reach agreement, you will make a fair determination of the Claims of the Contractor.
In your “Notice of the Employer’s Representative’s determination”, what is your determination for the Contractor?

 
 
 
 

新問題 32
There are four reasons that the Employer/Contractor shall advise in advance each other and the Engineer of any known or future events or circumstances.
Which two of the following statements areNOTapplicable reasons?
(Choose all correct answers – multiple possibilities)

 
 
 
 

新問題 33
Which of the following situations form legally binding contracts? (2 correct answers apply) Choose all of the correct answers (multiple possibilities)

 
 
 
 

新問題 34
Under the FIDIC Red Book (edition 1999): the Contractor submitted Final Statement in accordance with the Contract and the Contractor wants to correct it. Can the Contractor correct the Final Statement?

 
 

新問題 35
Under the FIDIC Red, Yellow, and Silver Books (both editions), the Employer has an obligation to give a detailed notice to the Contractor about intended changes that are material to its financial arrangements.

 
 

新問題 36
Under the FIDIC Construction Contract, which one of the following statements is correct?

 
 
 
 
 

新問題 37
You are the Contract Manager of the Engineer for a contract using FIDIC Yellow Book (edition 2017). You are drafting a notice holding the Commencement Date. Which one of the following approaches has the most clear and unambiguous drafting?

 
 
 
 

新問題 38
Which one of the following documents constitutes a contract and is considered binding on both parties, when the Employer wants to award the Contract to the tenderer?

 
 
 
 

Medical Professional Exams基礎問題CCM試験練習問題集:https://www.passtest.jp/Medical-Professional/CCM-shiken.html

         

Related Links: www.slideshare.net myportal.utt.edu.tt hashnode.com www.dibiz.com myportal.utt.edu.tt myportal.utt.edu.tt

コメントを残す

メールアドレスが公開されることはありません。 が付いている欄は必須項目です

Enter the text from the image below